Case Study



Title: Follow-Up - General Repair - Survey Construction Company
Scope: Partial Depth Repair
Purpose: Demonstration of Pavemend Materials in extreme cold weather application
Location: Ulaanbaatar, Mongolia
Date: March 30, 2004

PAVEMEND STUDY REPORT IN 22 DAYS AFTER TRIAL
Reported by Mr. Sakaba and Mr. Gotou, Suruga Mongol

Date of Inspection: April 21, 2004
Lapse of time after trial: 3 weeks
Ambient Temperature : 9°C.
Surface Temperature: Site A at 7°C.
Please refer to figures 1, 2 and 3.

No crack is observed either on surface or at joint in all the sites A, B and C respectively in 22 days after trial.In addition, no difference is observed in the appearance of each site between those in one week after trial, i.e. on April 7, 2004 and in three weeks after trial, i.e. on April 21, 2004. Please refer to figures 4, 5 and 6.


Figure 1:
Checking ambient
temperature at Site A

Figure 2:

Checking ambient
temperature at Site B

Figure 3:

Checking ambient
temperature at Site C

 

Figure 1:
Site A

Figure 2:
Site B

Figure 3:
Site C